Lao People's Democratic Republic
Peace Independence Democracy Unity Prosperity
Ministry of Finance — Department of Information Technology
No. 59/MOF-IT
Vientiane Capital, dated 11 August 2026
1. Overall progress for the month of July 2026 reached 68% against a planned 72%, a variance of -4%.
2. Transformer bay foundations were inspected on 22 July and accepted without remarks.
3. Delivery of the 115kV switchgear has slipped by two weeks due to customs clearance at Thanaleng.
4. Requested action: approval of the revised milestone schedule attached as Annex A.